Use the minimum set that preserves record ownership and reliable reporting.
TabCore fieldsReview questionMove to workflow software when
ProjectsProject ID, owner, site, manager, stage, baseline, forecast, health.Which projects need a decision now?Several teams edit status or require permissions.
Milestones and commitmentsProject ID, package, owner, baseline date, forecast date, status, dependency, recovery.What is late or threatened and who owns recovery?Reminders, returns, mobile updates, or history matter.
RFIs, changes, and risksRecord ID, type, description, reviewer, due date, impact, decision, response.Which decision or exposure can change cost or completion?Attachments, approvals, linked actions, and audit history grow.
Costs and forecastPackage, budget, commitment, approved change, pending exposure, actual, forecast, action.What explains movement from budget to forecast?Finance integration, access control, and governed approval are required.
Bids and subcontractorsPackage, bidder or trade, dates, qualification, submission, exclusions, score, award or readiness status.Which bid or trade needs clarification, review, or a decision?Many bidders, files, reviewers, reminders, and award handoffs must stay coordinated.
Time and field expenseWorker or crew, project, cost code, date, hours, overtime, expense, evidence, reviewer, status.Which entries are missing, unusual, returned, or ready for payroll and cost review?Mobile capture, permissions, approval, payroll handoff, and history matter.
SubmittalsPackage, spec section, revision, reviewer, required date, response, release, procurement impact.Which review is late and what work or procurement does it block?Files, revisions, parallel review, return cycles, and downstream actions grow.
DashboardDefined measures linked to filtered source rows.Can every signal open the work behind it?Manual refresh and copied totals reduce trust.